2018 05 04 Concrete Drive, Flooring

2018 05 04 Concrete Drive, Flooring

Half the concrete pad in front of the garage and utility area is poured, and flooring work continues.

The concrete has a color that is meant to be close to some of the rock in the gabion walls, which all came from the site.  I was not able to photograph all the grading work.


The two steel posts are part of the rolling gate.  It will have a big concrete footing.



All the concrete in the utility area had to be brought over in a wheelbarrow.




The gate footing again.





The gate footing again, again.




Meanwhile, the floor progresses.


The pieces of blue tape on the walls mark small flaws.