2018 03 30 Gabion Walls Done, Fixtures, Tile, Deck Tile, More ..
The gabion walls are now done, and they look great. One of these walls is just behind (north) of the solar array, so work on that can begin soon.
Deck tile has arrived and work will begin on that soon.
Inside, light fixtures are going in, and although most of the lighting controls are not in, some of the lights are switchable and can be seen. I will go to the house at dusk one day next week.
Most of the bath tile is done.
The water pressure tank is in, and the well technician will work with the plumber to get the water on very soon. The ground source heat pump system will be "charged" soon.
First three photos show lights going into the main living space. The kitchen island has been faced with the same steel used on the exterior.
Some of the deck tile placed near the pool. Pool guys have resumed their work.
Three photos of "her" bath. Tile work is done.
Next two show the aluminum shoe that will hold the glass rail on the east deck.
Next two show solar field to the west of the house. Wall is done! Pile of stuff is solar panels and some of the frames for them.
More "stuff" under the house. First is pressure tank next to the well pipe.
All the pretty copper GSHP plumbing has been insulated.
Some of the lighting control was brought down here.