2017 10 23 Sheetrock, grading ..
Sheetrock work, grading around the walkway and trellis foundation. The small trench compactor in the second and third photo is run with a remote control, which looks like fun. All the remaining dirt that was taken out of the foundation dig is being "exported". The remaining rock will go into the gabion walls that are not yet built.
Saturday, October 28, 2017
2017 10 19 Details, walkway foundation, weather ..
2017 10 19 Details, walkway foundation, weather ..
First photo is some of the avalanche of lighting and lighting control wiring.
Second is all the lighting cans in the hallway. The installer did a great job getting these right in spite of all the joists and other "stuff" in the ceiling.
This photo is an extreme example of the shim work that goes into getting the walls flat before sheetrock.
Fourth photo is the walkway foundation, last two are weather at the end of the day. It snowed in Truckee that night.
First photo is some of the avalanche of lighting and lighting control wiring.
Second is all the lighting cans in the hallway. The installer did a great job getting these right in spite of all the joists and other "stuff" in the ceiling.
This photo is an extreme example of the shim work that goes into getting the walls flat before sheetrock.
Fourth photo is the walkway foundation, last two are weather at the end of the day. It snowed in Truckee that night.
2017 10 18 Walkway foundation, sheetrock ..
2017 10 18 Walkway foundation, sheetrock ..
Concrete is poured for the walkway trellis that extends out from the front door.
Sheetrock progress.
Concrete is poured for the walkway trellis that extends out from the front door.
Sheetrock progress.